INDEPENDENT LOCAL HOUSING ANALYSIS
MISSION, BRITISH COLUMBIA
HOUSING SUPPLY / UPDATED SEPTEMBER 24, 2026

THE BUILDING SIDE OF THE MARKET

Mission's housing target has a longer clock.

The provincial order sets a five-year minimum of 1,798 net new homes. Mission reported 314 in the first year, exceeding its 211-unit year-one target.

Five-year target
1,798
Net new homes by 2029
Year-one target
211
Reporting year ending July 31, 2025
Year-one result
314
103 above the year-one target

What counts here?

The 314 figure is net new homes, after accounting for demolitions, over August 1, 2024 to July 31, 2025. It is not permits issued or MLS listings added. The City reports 338 completions and 24 demolitions in the period.

Completing 17.5% of the five-year total in year one does not establish the current pace in September 2026. This page will need a newer progress report before making any claim about year two.